Two 35TB migrations

Same volume, one weekend versus three months and three aborted attempts. The variable was the data model.

Two migrations, same size, opposite outcomes.

The first: a Friday morning note telling me that 35TB of call detail record data I had been expecting the following month had arrived early. Around 20,000 compressed files, well formatted, sensibly named. We had no load process at all. I spent the day writing shell and Perl — this was a while ago — that generated SQL to load the files in parallel, straight into the database without uncompressing them first. I started the job at 4pm on the Friday. I came in on Monday and the whole 35TB was loaded and usable.

The second: a 35TB reporting system, a few hundred tables, migrated with the standard recommended toolset. Three months and three aborted attempts before the database was finally across.

Identical volume. One completed over a weekend with a script written in an afternoon; the other took a quarter of a year with proper tooling and experienced people. The difference was not size, skill, budget or product. It was the data model.


Where this feeds the guide: Complexity, not volume and Nothing survives twelve hours.

Reviewed 25 August 2026

These are my own views, written from years of building and moving large Oracle data platforms. They are not Oracle’s official guidance and this is not Oracle documentation. Volatile product claims are quarantined in Product facts that will date.