Cutover and rollback template

Checkpoints, evidence and decision owners for the window.

Cutover checkpoints, the evidence for each, and who decides
CheckpointEvidence reviewedDecision owner and action on failure
Pre-cutover readinessChange freeze, communications, access, source recovery position, rolesRelease authority: proceed, defer or reduce scope
Final consistent pointFinal backup, extract watermark or replication positionMigration lead: verify or stop
Abort milestoneDefined progress point reached by the pre-agreed time, measured against timed rewind durationNamed abort authority, acting alone: continue or rewind
Target readinessLoad or catch-up complete, validation thresholds met, security checksData and security owners: accept or remediate
Business releaseCritical business and workload checks acceptedBusiness owner: release or extend validation
Rollback boundaryThe explicit condition beyond which return is unsafeNamed authority: consciously accept the crossing
HandoverMonitoring, support and defect ownership acceptedService owner: accept or retain migration control

Record times, evidence, participants and decisions as cutover proceeds. In the rollback section, describe how the source is preserved, how target writes are handled, who is informed, the recovery sequence and the latest safe time for the decision.